087 2373668 [email protected]

Project Description

Alterations and Extension to Existing Primary School Building at Bohermore NS, Bohermore, Co Limerick

Contracting Authority

Bohermore Board of Management

Contracting Authority Representatives

James Corbett Architects
11 The Crescent,
O’Connell Street,
Limerick V94 V2VW

Start Date

23 May 2019

Completion Date

14 February 2020

Services Provided

Main Contractor & Project Supervisor Construction Stage. i.e. site safety set up, excavation, foundation, block work, roofing, plastering, supervision of M&E Sub Contractors, installation of new windows & doors, 2nd fixing, installing disabled access WC & Shower Room, painting, and fitted furniture fit out, including all associated site works.